Burton Joyce Online

  • Increase font size
  • Default font size
  • Decrease font size
Home Village Groups Residents Association
BJ Residents Association

The Burton Joyce Residents' Association exists to protect, preserve and enhance the lovely riverside area in and around Burton Joyce. It is open to anyone who shares our objectives.



Minerals, waste & Floods

These are verbatim notes of the updates from BJ residents Association  

Pumping station news

A question arose at the recent AGM about the operational status of the new pumping station.

The pumping station is operational but relies on using a mobile generator at present.  The Environment Agency is gradually resolving land-ownership issues which, when sorted out, will allow them to make the mains electricity connection to the pumping station.

The remaining metal screens around the substation area will be removed when the mains connection works at the substation are complete.  When EON has finished installing the substation and mains electricity, shrubbery will be planted to screen the installation.

With many thanks to Innes Thomson, Area Flood Risk Manager at the Environment Agency for this information

Annual Report 2009

The past year has been exceptionally quiet but throughout we have continued to keep a watchful eye on potential developments on our riverside area.

Nottinghamshire County Council - Minerals and Waste Development Framework.

The timetable for the development of this framework, which will replace the current Minerals Plan, has slipped even further and there have been no developments this year.  The consultation had been planned for the second half of 2009 but our latest information is that this will begin in May 2010.  This stage may include designation of specific sites but even this is uncertain at this stage.  We are aware that a mining company has been holding consultations regarding possible future extraction of sand and gravel in Shelford but there has been no equivalent activity on this side of the Trent.

Flood protection.

Slipping timetables seem to have been the order of the day in 2009.  Early in the year I met officers from the Environment Agency to discuss issues concerning the proposed flood embankment.  It had emerged that the Environment Agency’s project to construct the embankment had met unexpected problems, further work on the design of the project was necessary and costs would be much higher than originally anticipated.  During the year the funding that had been agreed for the embankment in Burton Joyce planned to start in 2009 was withdrawn and spent elsewhere.  This resulted in us embarking on a flurry of inquiry and activity and eventually the EA advised that funding totalling £490,000 had been agreed for the embankment and it was hoped that work would commence in the spring of 2010.

Restoration of the old gravel workings.

Severn Trent Water’s failure to restore the old gravel workings at Gunthorpe and Bulcote, and the County Council’s failure to enforce Modification Orders has been a continuing issue of concern this year.  There have been a number of meetings on this issue with, as yet, no outcome.  The indefatigable Roger Fell has been leading on this issue in which the effect of non-restoration on flood storage capacity and potential for future flooding is particularly relevant.  Many thanks are due to Roger for his extensive and ongoing work in this area.

Surveys.

This year with the help of Carol Wright, I undertook a survey of the flora on the Burton Meadows loop with a view to establishing if there was sufficient variety of flora to enable this area to be re-instated as a Sites of Interest to Nature Conservation (SINC, now renamed as Local Nature Areas).  We submitted the outcome to the Biological Records Office at Wollaton Hall but were later advised that the flora we had recorded did not enable the area to be redesignated.  We shall continue this survey this year with the hope of identifying other flora we may have missed.  Many thanks to Carol for her invaluable help with this work.

I also undertook a survey of the condition of footpaths and bridleways on the riverside, extending this to all footpaths in Burton Joyce and Bulcote in order to contribute to the work of Nottinghamshire Ramblers in recording footpath condition.  Generally the footpaths are well kept.  Thanks are due to the various landowners for this.  A report and requests for the renewal of signage and improvement to one bridleway in poor condition were made to Nottinghamshire County Council.  The County Council responded with the hope that they would be able to put the requests on the programme for the current financial year but to date no action has been observed.

Consultations.

As usual, we have read a number of consultation documents and made responses to the following:

·          Gunthorpe Gravel Pits restoration proposals

·          Greater Nottingham Core Strategy: Issues and Options

Information.

We have continued to display news updates on our website (www.bjra.org.uk) to enable everyone to have access to up-to-date news.

Contacts with other organisations.

We have continued to be in active contact with many other individuals and organisations – most notably this year with The Undefended Village Partnership, Roger Fell and our MP Vernon Coaker.  Our thanks to all for the support and encouragement that is engendered though this ongoing co-operation and exchange of information.

As always, at our AGM, we shall be electing Officers and Committee members.  Last year I reluctantly took on the post of Chairman again in view of ongoing health problems and advised that I would not be standing for re-election to this post again.  After five years as Chairman, it is time for someone else to take the lead.  I would urge all members to consider if you can contribute to the active work of the Association by offering yourself as one of the Officers or Committee members.

Julie O’Neill

Consultations on Minerals and Waste sites delayed We reported earlier this year that the next stage of public consultation in the Minerals and Waste Framework would take place in October for Waste and November for Minerals.

We now learn that the schedule has slipped yet again and the next stage will not now take place until sometime in the new year.  It is not now clear at what stage specific sites will be allocated.  It may, or may not be, at the next consultation stage – so watch this space for further developments

posted by JO @ Wednesday, October 21, 2009

Flood embankment to be started in Spring 2010

We recently reported that the funding for Burton Joyce Flood Embankment had been allocated elsewhere and that we were seeking assurances that our flood embankment will still go ahead.  We are very pleased to be able to report that the Regional Flood Defence Committee has now allocated £490,000 for the Burton Joyce Flood Embankment and the Environment Agency aims to commence construction in Spring 2010.

Many thanks are due to Vernon Coaker, our M.P., for obtaining this information from the EA when a direct request for information from us received no response.  Also to the indefatigable Roger Fell for beavering away to get an assurance that all the promised flood mitigation measures downstream of Nottingham will be carried out before work is completed on the Nottingham Flood Alleviation Scheme

 

BJ Flood Embankment latest

Flood embankment news

(This information is kindly made available to us by BJRA and is reproduced verbatim)

We were very disappointed to learn last week that the money allocated by the Environment Agency last year for the construction of a new flood embankment for Burton Joyce has now been allocated elsewhere.

As reported on this web-site last May, the Environment Agency had met unexpected problems with the provision of this flood embankment and that the project was likely to be far more expensive than originally anticipated.  At that time, however, we were assured that the flood embankment would go ahead nevertheless.

We are now making inquiries about this matter and seeking confirmation that funding will be made available to provide flood defences for the village in the future.

 

Footpaths and bridleways in Burton Joyce and Bulcote

Earlier this year we undertook a survey of the 12 footpaths and 9 bridleways in Burton Joyce and Bulcote, subsequently sending a list of suggested repairs and signing improvements to Notts County Council.  We have now had a response from the Rights of Way officer saying that she hopes to be able to address the signposting and waymarking issues when she compiles a signposting contract later on during this financial year. She will also look at the one footpath we reported as in poor condition in due course.

Our claim for the reinstatement of an old footpath, which had not been shown on the definitive rights of way map, made as a result of a previous footpath study in 2004 has been accepted by the County Council and agreed by the Inspector at a public inquiry.  It will be reinstated as soon as funds are available. This will provide a route from the Trent at the point where the Cocker Beck enters the river at the junction of Bulcote and Gunthorpe parishes to the A 6097 at Lowdham Leisure World, passing the fishing lakes.  This will be an alternative and hopefully attractive route into Gunthorpe by public footpath and will be particularly useful when high water makes it impossible to use the other public footpath which passes under Gunthorpe bridge.

Our thanks to Nottinghamshire County Council and local landowners who generally keep the footpaths and bridleways in a good condition and to the County Council for taking our reports on board.

----------

 

Revised BJPC Accounts

REVISED BJPC 2008/09 Accounts 

A simplified version of the Parish Council’s income and expenditure for 2008-9 was posted in the Other Village News section last month.  This was extracted from April 2008-March 2009 Income and Expenditure Accounts as presented to the Council in May.  On examining the accounts made available for public inspection recently, it was found that a new version of the accounts had been prepared.  This is now posted below and replaces the earlier posting.

Anyone who is interested in examining the accounts and any associated documentation still has until 24 July to do this.  See Parish Council notice-board for details of access.

Revised version of Parish Council accounts for 2008/9

Income: 

Parish precept       59,361

Grant - Gedling BC   28,673

Cemetery             10,129

Allotments           1,693

Sports ground        8,880

Playscheme           662

Bonfire              1,323

Gala                 828

Donations, other    1,912

Interest             586

Capital aid          22,731

 

Total         136,778

 

Expenditure:

Wages                55,757

Administration       12,270

Parish Office        2,306

Cemetery             622

Allotments           1,553

Sports ground        22,695

General maintenance 8,396

Playscheme           725

Bonfire              1,199

Training             330

Donations            275

Chairman-allowance   50

Councillors-expenses 67

Capital expenditure 15,217

Total         121,462

posted by bjra @ Monday, July 07, 2008

 

New Consultations

New consultations

We are currently studying two new consultation documents.

There is a new consultation on restoring the Gunthorpe Lakes area following minerals extraction that ceased several decades ago.  There have been a number of previous consultation documents and this one says little new.  Julie has a copy of this consultation if you would like to see it.  Comments must be submitted by 23 July.

There is also a consultation from Gedling Borough Council “Greater Nottingham Core Strategies: Issues and Options”  This deals with planning issues for the Greater Nottingham area over the next 20+ years including issues such as housing, economic growth, employment, transport, green infrastructure and the Green Belt and climate change.  There is a separate section for Gedling issues.  There is a copy of this consultation in the village library and on the Gedling Borough Council website.  Comments must be submitted by 31 July.

We shall be responding to these consultations as usual in respect of issues that relate to the role of our Association.  Anyone can respond individually to these consultations but members can also send their comments for inclusion in the BJRA representation.  Please send any comments to our contact address at least a week before the final submission date stated above.

 

 

AGM 2009

Seventh Annual General Meeting

The A.G.M. took place on 12 May with reports and accounts presented for the past year and officers and the committee was duly elected for the forthcoming year.  Julie O’Neill was elected as Chairman, John Byron as Vice-Chairman, David Prime as Secretary and Tony Simpson as Treasurer.

The Chairman reported on events of the past year and future developments to be carefully monitored.  Vigilance is the key, for although Tarmac has withdrawn its application for minerals extraction at Bulocte Farm, Nottinghamshire County Council has carried over the Gunthorpe allocation in the Minerals Plan for the future after its expiry date in December 2008.

As things stand, the whole consultation and site consideration process begins again in August for Waste Issues and in October for Minerals Issues.  We shall be studying any proposals in both these areas, especially to see if any attempt is made to re-allocate the Gunthorpe site for minerals extraction.  In March 2010, more specific studies for Waste Issues will begin and in May 2010 a similar process for Minerals extraction will begin. The Association will need to be fully prepared and informed to examine any proposals at this time and to raise objections to any aspects considered unacceptable.

We feel that Burton Joyce residents may have been lulled into a false sense of security over the Gunthorpe allocation in the Minerals Plan.  The threat has not gone away.  Many factors may change during the present period of allocation which does not end until September 2012.  The Association will remain vigilant and alert as proposals and information unfold and will keep residents informed of all future developments. Residents would be wise to remain informed and involved with the process; it’s the best defence against threats that the village still faces.

We had more positive outcomes to our work on flooding issues in co-operation with other groups concerned about flooding in the Trent Valley.  The Environment Agency has committed to providing a new flood embankment for Burton Joyce that will run from the level crossing on Station Road to the new pumping station. This will offer flood protection to part of the village. As is often the case, there have been unforeseen technical problems and increased costs but we have received assurances from the Environment Agency that the work will definitely go ahead.

Our Chairman attended the Annual Parish Meeting on May 19th and reported on the current situation and our activities over the past year.

David Prime, Secretary.

posted by JO @ Thursday, June 25,
 
  • «
  •  Start 
  •  Prev 
  •  1 
  •  2 
  •  Next 
  •  End 
  • »


Page 1 of 2